The Caltrain Modernization Program (CalMod) is a $1.9 billion project that will add a positive train control (PTC) system and electrify the main line of the U.S. commuter railroad Caltrain, which serves cities in the San Francisco Peninsula and Silicon Valley, as well as transition from its current diesel-electric locomotive powered trains to electric multiple units (EMU). According to Caltrain, electrification of the tracks will allow it to improve service times via faster acceleration and shorter headways, reduce air pollution and noise, and facilitate a future railway tunnel (the Downtown Rail Extension) into downtown San Francisco's Transbay Transit Center (as diesel trains cannot serve underground stations).
Proposals for electrifying the line began as early as 1992, when the California Department of Transportation conducted an early feasibility study. For two decades, the project lay dormant due to lack of funding until Caltrain agreed to share its tracks with the California High-Speed Rail Authority (CHSRA), which was looking for a route for the constitutionally-mandated San Jose--San Francisco segment. The Authority agreed to partially fund the electrification project in exchange for rights to share the track. Construction contracts for electrification were awarded on July 2016 and groundbreaking was expected to occur in March 2017, but was delayed when the new United States Secretary of Transportation Elaine Chao indefinitely deferred federal funding just before construction was about to begin. That same month, Caltrain removed the contractor responsible for implementing PTC for failure to perform on-budget and on-schedule. In May 2017, the Federal Transit Administration's (FTA) announced its intention to sign the grant and reversed Secretary Chao's deferment. Construction formally began two months later.
When completed, CalMod will electrify 51 miles (82 km) of tracks between 4th and King station and Tamien Station and install a PTC management system along the tracks. PTC is designed to fulfill federal safety mandates for passenger rail and is part of the Federal Railroad Administration (FRA) waiver to use EMUs on tracks shared with freight traffic. Funding for the project comes from various federal, state, and local sources, including from the CHSRA. Caltrain plans to complete the project by 2021, after which it plans to use double-decker EMU Stadler Rail trainsets on the electrified route. Some of the diesel locomotives will be retained for service south of Tamien.
Video Electrification of Caltrain
History
Background
Commuter railroad service on the San Francisco Peninsula was inaugurated in 1863 as the San Francisco and San Jose Rail Road and purchased by Southern Pacific (SP) in 1870. SP announced that it would investigate the electrification of its line in September 1921, promising better and more frequent service. However, SP cited excessive post-war inflation, taxation, and competition from publicly-funded highways as factors making electrification neither "practicable or desirable". In the early 1950s, SP began introducing diesel locomotives on the route. By 1977, Southern Pacific were facing rapidly declining ridership and petitioned the state Public Utilities Commission to allow them to discontinue the commuter rail operation. From 1980 until 1992, the California Department of Transportation (Caltrans) and the three service counties, San Francisco, San Mateo, and Santa Clara, subsidized Southern Pacific operations on the railway until the local Peninsula Corridor Joint Powers Board (PCJPB) acquired the right-of-way in 1991.
Early electrification proposals
In 1992, Caltrans released the first feasibility study detailing the possibility of electrifying the railroad between San Francisco and San Jose. The 1992 Feasibility Study proposed replacing the existing diesel-electric locomotives with either a fleet of EMD AEM-7 electric locomotives to move the existing gallery passenger cars or Metro North Budd M-2/M-4 EMUs. The primary benefits of an electrified railway would be improvements in air quality, noise, and acceleration, but would also save on other ancillary costs, such as lubricating oil, cooling water, maintenance, and refueling. Because of the relatively close spacing between stops, the improved acceleration using electric locomotives compared to the existing diesel-electric locomotives would cut transit time between San Francisco and San Jose by up to twelve minutes, and using EMUs would cut the time over the same distance by up to 23 minutes, assuming the use of ten-car trainsets. The 1992 Feasibility Study recommended the use of electric locomotives and 25 kV AC overhead lines as the most cost-effective alternative, since the gallery cars, which had been built in 1985, were then relatively new and could be reused.
Due to funding shortages, the project was postponed for the next two decades. In 1997, Mayor Willie Brown canceled the appropriation for San Francisco's share of costs to extend rail service to downtown, saying Peninsula residents "ought to fund the whole project" since it would mainly benefit their commute. San Francisco instead applied the money to the Third Street Light Rail Project. Mike Nevin, PCJPB member from San Mateo County noted that while the downtown extension "would have enhanced particularly the electrification of the system", lack of it would not cause Caltrain to collapse. Instead, Caltrain studied a list of potential upgrades and went on to publish a draft Rapid Rail Study on October 1, 1998, which prioritized capital improvements to the physical infrastructure with the overarching goal of expanding rail service. At that time, Caltrain was reporting daily ridership of approximately 25,000 passengers, a 40-year high.
The 1998 Rapid Rail Study assumed that ridership would increase in direct proportion to improving travel times. The study concluded that in order to meet the five goals presented in the 20-Year Strategic Plan of 1997, Caltrain should first rehabilitate and enhance the line, then electrify it. By itself, electrification was not projected to significantly improve service, and the high estimated cost of electrification and its lower priority meant electrification would be deferred. Some of the money to accomplish the rehabilitation and enhancement of existing track came from funds that had been intended for the downtown extension. Steve Schmidt, a councilman from Menlo Park, argued that electrification instead should be the top priority to make the rail line more palatable to neighbors, citing improvements in noise and pollution. Other advocates for electrification of Caltrain noted the $1.2 billion BART extension to San Francisco International Airport may have revived the decades-old dream of BART around the Bay, which would render an electrified Caltrain redundant. The electrification of Caltrain was assigned a higher priority than a future expansion of the system, which included proposals to bring service to Union City across the Dumbarton Rail Bridge and increased service to Gilroy. Under the latest proposal to revive rail service over the Dumbarton Rail Corridor, diesel multiple units would first be used to establish Dumbarton Rail service as a rail shuttle between a new rail station in Newark and Caltrain's Redwood City station, later extending service from Newark to Union City, and finally followed by a commuter rail operation running from Union City to San Francisco and San Jose using EMUs.
In 2003, The San Francisco County Transit Authority proposed Proposition K in San Francisco, a local transportation sales tax. Voters were given an expenditure plan estimating the total cost of Caltrain electrification as $183.5 Million with San Francisco's share costing $20.5M, met with Proposition K, which passed..
Caltrain/HSR blended system
Despite increasing ridership, Caltrain experienced a budget crisis in 2011 that nearly forced it to cut service to peak commute hours only, while funding sources for electrification remained unidentified. At the same time, the California High-Speed Rail Authority (CHSRA) was having trouble identifying a route from San Jose to San Francisco in the face of local opposition. In response, U.S. Representative Anna Eshoo, State Senator Joe Simitian, and Assemblymember Rich Gordon announced a "blended" plan to partially fund electrification with high-speed rail money in return for allowing high-speed rail trains to share tracks in the future. Later, Caltrain announced that it had studied the plan and believed it to be feasible.
Under a proposed agreement between Caltrain and the CHSRA, details of which were leaked in February 2012, up to $1 billion could be available from the high-speed rail project to help fund the CalMod project, including the positive train control system (dubbed "CBOSS"), electrification of the infrastructure, and elimination of some grade crossings. Under the agreement, the Peninsula Corridor would become eligible for high-speed rail money because the planned routing to San Francisco would use the same lines. This was one of two investments in "bookend" electrification projects, which were intended to upgrade existing passenger rail services near the planned CHSRA San Francisco and Los Angeles terminals to allow high-speed rail to share infrastructure. In March 2012, Caltrain and other local agencies signed a memorandum of understanding with the CHSRA that detailed the blended plan, which received approval from the Metropolitan Transportation Commission a week later.
Under the memorandum, $706 million from the high-speed rail bond would be matched by state, regional, and local transportation funds to pay for the estimated $1.5 billion needed for CalMod. However, since the bonds had not yet been issued, the money was not available, and a prior environmental impact report that had been issued for electrification in 2009 needed to be reissued before construction could start. In September 2012, the California Transportation Commission released $39.8 million to modernize CBOSS. A month later, the expected funding from high-speed rail bonds rose to $1.5 billion, which alongside electrification provided funding for the planned Downtown Extension (DTX), which would move the northern terminus of the Caltrain line from 4th and King to the Transbay Transit Center. CHSRA approved the issue of bonds in December 2016. Critics of high-speed rail felt the slower trips and reduced service caused by "blending" the two systems over the Peninsula Corridor did not meet the original voter-approved vision of a quad-track line between San Francisco and Los Angeles, and ridership would never meet projections.
Lawsuits
The town of Atherton, which lies on the tracks, was an early and vocal opponent of electrification. Residents opposed electrification and the proposed high-speed rail route because the overhead electrical lines would require tree removal and the town could potentially be divided in two by permanently closing the two grade crossings at Fair Oaks Lane and Watkins Avenue.
In February 2015, shortly after the project received environmental clearance from California, Atherton sued Caltrain, alleging the agency's environmental impact review was inadequate and that its collaboration with the CHSRA should be further vetted. In July 2015, the suit proceeded after Caltrain's request to the Surface Transportation Board to exempt it from California Environmental Quality Act (CEQA) guidelines was denied. Atherton reiterated its opposition to electrification on the basis that overhead wires would require removing a significant number of heritage trees, and city representatives asserted that "newer, cleaner, more efficient diesel trains" should supplant plans for "century-old catenary electrical line technology." Atherton mayor Rick De Golia was quoted as saying "Caltrain is locked into an old technology and 20th century thinking." After Caltrain issued infrastructure and rolling stock contracts in July 2016, Atherton representatives did not file a temporary restraining order to halt those contracts, preferring to let the suit proceed to a hearing. In September 2016, Contra Costa County Superior Court Judge Barry Goode sided with Caltrain, ruling that the electrification project did not hinge on the high-speed rail project's success, and was thus independent from the latter.
Indeed, at bottom [California High-Speed Rail] is providing funds to Caltrain while hoping that the rest of CHSRA's plans work out well enough that, someday, it can bring the blended system to fruition. But if CHSRA is unable to do that, Caltrain will still have a successful project. Put another way, HSR may need to have Caltrain's Electrification Project completed. But Caltrain does not need to have High Speed Rail completed for the Electrification Project to be a success.
Atherton sued CHSRA again in December 2016, stating that using bond money intended for high-speed rail for CalMod was a material change in usage and therefore was unconstitutional because such a change would require voter approval first. In response, the California legislature allowed the funding to be redirected by passing Assembly Bill No. 1889, which had been championed by Assemblymember Kevin Mullin in 2015. Mullin noted "this entire Caltrain corridor is the epicenter of the innovation economy and it's a job creation and economic engine. This electrification project, I would argue, is monumental with regard to dealing with [increased traffic and environmental impacts] effectively and efficiently."
Contracts awarded
Parsons Transportation Group was awarded a $138 million contract in November 2011 to design and install CBOSS by October 2015. Parsons began physical work on CBOSS in September 2013, starting with the installation of a fiber optic line along the Caltrain right-of-way. The Federal Railroad Administration (FRA) approved Caltrain's plans in 2014 and Caltrain noted that CBOSS was due to enter revenue service by the end of 2015. Because Caltrain had multiple goals for CBOSS, including increased safety, improved operational efficiency, and ensured interoperability with other rail providers (Caltrain shares tracks with Union Pacific, Altamont Corridor Express, and Amtrak), implementation was challenging and Caltrain, the busiest commuter rail service on the West Coast, still had not fully implemented the system by the end of 2016.
The Peninsula Corridor Electrification Project (PCEP) draft environmental impact report was released in February 2014. After addressing comments received, PCJPB certified the final environmental impact report in January 2015. A pre-qualification survey was sent out in May 2014, and six firms were pre-qualified to bid on PCEP construction, which was eventually awarded to Balfour Beatty Construction.
In July 2016, Caltrain's Board of Directors awarded contracts to Balfour Beatty and Stadler Rail to construct infrastructure for the electric trains and the electric trains themselves, respectively. Balfour Beatty was awarded a $697 million contract, its largest contract in the United States, to electrify the line at 25kV AC, replace signaling systems, construct two traction power substations, one switching substation, and seven paralleling substations. The Swiss firm Stadler was awarded a $551 million contract to deliver 96 of their "KISS" bilevel electric multiple unit cars, formed into 16 six-car trains. Under the contract, Caltrain holds an option to increase the order with an additional 96 cars in the future. The contract also marks the first American design win for the Stadler KISS. Stadler broke ground for a new factory near the Salt Lake City International Airport on October 13, 2017. The first trains are scheduled for delivery in August 2019.
In April 2016, after missing the initial October 2015 deadline, Caltrain requested a third party review of the CBOSS project from the American Public Transportation Association (APTA). APTA noted that Caltrain was not effectively managing the project schedule and cost because of generally poor communication between Caltrain's project management and Parsons, and Caltrain's project manager did not have the technical experience or authority to resolve technical and contractual issues with Parsons. In February 2017, Caltrain terminated its contract with Parsons for failure to perform on time and budget and announced potential litigation. Parsons filed suit on February 22, saying delays were due to changing client requirements and circumstances beyond their control. Caltrain filed suit a week later, seeking $98 million in damages; although the system has been mostly installed, testing is still incomplete.
The plan to complete the installation of positive train control (PTC) will be presented to PCJPB in early 2018. At the March 1, 2018 meeting, the PCJPB is expected to vote on awarding the contract to complete PTC to Wabtec. The switch to Wabtec would mean implementing I-ETMS technology, which was evaluated to be "the only technically and financially viable" solution to completing PTC before the FRA's deadline of December 31, 2018.
Federal funding interruption
In early 2016, the CHSRA had selected a route that required extensive and costly tunneling in Southern California and revised its initial operating plans for high-speed rail to include the Bay Area. By February 2017, the electrification project had secured $1.3 billion in state, local, and regional funding, with the remaining funding gap to be closed by a $647 million grant from the FTA's Core Capacity program. The grant had undergone a two-year review process starting in November 2015 under the Obama Administration and received a "medium-high" rating from the FTA in August 2016, and was waiting for a signature from the newly-appointed Trump Administration Secretary of Transportation Elaine Chao after a 30-day review period to secure a grant approval. However, during the review period, the fourteen Republican party U.S. House representatives from California sent a letter to Secretary Chao, urging her to deny funding due to the project's ties with high-speed rail, which they opposed. The letter went on to call the project "an irresponsible use of taxpayer dollars".
The Sacramento Bee pointed out that despite regularly soliciting campaign funds from Silicon Valley business leaders, Representative and House Majority Leader Kevin McCarthy, the author of the Republican letter to Secretary Chao, was targeting a project that benefited the region directly. Another Republican signatory, Representative Devin Nunes, was unmoved by arguments on infrastructure benefits, saying in late February that he would not "feel too bad about one of the richest places on the planet not having a train." Fellow Republican Representative Jeff Denham defended the letter, saying Caltrain's electrification project and CHSRA were closely intertwined because the former derived some funding under the "blended plan" agreement. Representative Tom McClintock reiterated his opposition to high-speed rail without addressing Caltrain: "I have never supported a dollar of state funding going for [high-speed rail], and would never support a dollar of federal funding." Representative Mimi Walters also made a statement that she was not opposed to electrification, but instead held "serious concerns about the use of taxpayer funds for a project that is tied to high speed rail".
The 39-member House and Senate Democratic congressional delegation from California wrote a rebuttal letter to Secretary Chao on February 3, noting "a material misstatement of fact" in the Republican delegation's letter, which stated that the grant was being sought by the CHSRA, while in reality it is being sought by Caltrain. The rebuttal letter further delineated the separation between the electrification project and CHSRA and urged Secretary Chao to approve the grant by citing past precedent that only one low-rated project failed to receive a signature from the Secretary of Transportation over the prior twenty-year history of the Core Capacity program. The Democratic letter went on to note the infrastructure benefits of the project and the creation of 9,600 jobs, including 550 jobs at a new Stadler USA plant in Salt Lake City.
In the end, Secretary Chao heeded the Republican letter's arguments, and deferred the grant in a letter written by FTA Executive Director Matthew Welbes to Caltrain which stated the FTA needed "additional time to complete review of this significant commitment of Federal resources". Caltrain had expected Secretary Chao to approve the grant and sign the grant agreement by March 1, which is normally a pro forma step performed after the thirty-day comment period for a highly-rated project, and had already awarded construction contracts. Balfour Beatty Construction and Stadler Rail had already begun preparations to upgrade the existing tracks and build electrical trainsets, respectively. Caltrain negotiated an emergency four-month contract extension at a potential cost of $20 million. Under the preliminary budget proposal released in mid-March 2017, the United States Department of Transportation's Capital Investment Grant Program would be eliminated, although approved projects would continue to be funded. Since Secretary Chao had withheld grant approval for the electrification project, its future fell into doubt.
In response to the grant deferral, various local officials traveled to Washington D.C. in order to lobby federal officials to release the money. Editorials in local and national newspapers urged approval of the grant, including the Sacramento Bee, which called the deferral "a petty attack", the East Bay Times, a noted CHSRA detractor, and The New York Times, which called the delay "counter to Mr. Trump's campaign promises of increased infrastructure spending." Henry Grabar noted the grant deferral could be "an early test of a simmering fear that the state's outspoken political opposition to the Trump administration might come with a price". San Jose Mayor Sam Liccardo met with Department of Transportation officials, urging them to upgrade a system that "was built under the presidency of Abraham Lincoln". Additionally, more than 120 Silicon Valley business leaders sent a letter to Secretary Chao, asking her to explain "the last-minute attempt to derail two decades of work". In early March, California Governor Jerry Brown sent a letter to Secretary Chao, asking to discuss the funding grant, and subsequently met with Secretary Chao and Representative McCarthy, urging them to reconsider the funding deferral, saying afterward that he was "cautiously optimistic" that the money would be released.
On April 30, legislators in the U.S. Congress released the proposed 2017 federal budget, which included partial funding for the electrification project, but restricts its distribution unless Secretary Chao signs off on the grant. The proposed budget includes $100 million of the $647 million grant, with the balance expected in future years. Secretary Chao claimed she could not sign the grant without the full grant being budgeted, which was disputed by Caltrain and both California Senators Dianne Feinstein and Kamala Harris. On May 22, the FTA announced its intent to sign the funding grant, restoring the final piece of funding for the electrification project. The official grant was finally signed on May 23.
Electrification Expansion
In January 2018, PCJPB applied for $631.5 million in state funds for the Electrification Expansion Project (EEP), part of which would be used to exercise the option to purchase an additional 96 EMUs at a cost of $600M. The existing funding for PCEP includes the purchase of 96 EMUs, which would displace 75% of the current diesel-hauled passenger trains from the Peninsula Corridor. The additional funds requested for EEP would bring the electric fleet to 192 EMUs, enabling Caltrain to displace all diesel passenger locomotives between San Francisco and Tamien with a fleet of 24 8-EMU consists. $11.5M of the request would be used for station improvements: $8M to expand certain platforms to accommodate 8-EMU trains and $3.5M to increase secure bicycle storage. An additional $14M would be used to implement on-board WiFi for passengers. The remaining $6M would be used to support planning and policies along the Peninsula Corridor.
Construction
A new weekday schedule designed to allow time for construction became effective on April 10, 2017. The weekend schedule was revised on July 15, 2017, which decreased frequency from 60 minutes to 90 minutes between trains and eliminated eight trains per weekend day. The revised schedules are anticipated to be in effect until 2020, when construction associated with PCEP has completed.
An official groundbreaking ceremony was held on Friday, July 21, 2017 at the Millbrae station, attended by local and state officials, including Governor Jerry Brown; Representatives Anna Eshoo, Nancy Pelosi, and Jackie Speier; Senator Kamala Harris; State Senators Jerry Hill and Scott Wiener; Assemblymembers Kevin Mullin, Marc Berman, and Phil Ting; and San Francisco Mayor Ed Lee. In total, the ceremony had seventeen speakers celebrating the start of the CalMod project.
The PCJPB-owned right-of-way has been divided into four construction segments. From the north, the segments are arranged as:
- 4th and King, 22nd Street, Bayshore
- (South San Francisco, San Bruno); (Millbrae, Broadway, Burlingame); (San Mateo, Hayward Park, Hillsdale); (Belmont, San Carlos); (Redwood City, Atherton)
- Menlo Park, Palo Alto, Stanford, California Avenue, San Antonio, Mountain View, Sunnyvale, Lawrence
- (Santa Clara, College Park, San Jose Diridon, Tamien)
Segments are further divided into work areas, indicated by brackets in the list above. Work is scheduled to begin in Segments 2 and 4 and proceed from north to south within each segment before moving on to Segments 1 and 3. The first work area will be in the cities of South San Francisco and San Bruno. Within each work area, the first two months of activity will involve tree pruning and removal, followed by three to five months of construction of the foundations for the overhead contact system poles. Once the foundations are complete, construction of the traction power substation (if present) and pole and wire installation will work in parallel and take about a year. Schedules have been announced for Segment 2, Work Areas 5 (South City/San Bruno), 4 (Millbrae/Burlingame), 3 (San Mateo), 2 (Belmont/San Carlos), and 1 (Redwood City/Atherton). Segment/Work Area 4 (San Jose/Santa Clara) spans from Tamien to just north of the Santa Clara station, where the tracks diverge from the Union Pacific tracks near the overpass of De la Cruz Boulevard, and wire installation is scheduled to complete in late 2018.
In Segment 2, traction power substations (TPS) have been confirmed for South San Francisco and Burlingame, and another TPS will be located in San Mateo at a site yet to be named. In Segment 4, only San Jose will receive a TPS. In Atherton, 18 trees are planned to be removed with an additional 63 trees pruned more than 25%. 83 trees will be replaced as a result, per the Atherton Tree Replacement Plan.
When work is being performed at a station, both northbound and southbound trains will stop on the same platform to accommodate station construction. Signs will be posted to indicate which platform remains active for passengers.
Maps Electrification of Caltrain
Design
The Peninsula Corridor Electrification Project (PCEP) will electrify the entire 51-mile (82 km) right-of-way owned by the Peninsula Corridor Joint Powers Board (PCJPB), which extends from the San Francisco terminus at 4th and King to a power substation south of Tamien Station. New electrical infrastructure includes installation of approximately 130 to 140 miles (210 to 230 km) of 25 kV 60 Hz single-phase AC overhead contact lines and ten new power stations (two traction power stations, a switching station approximately halfway along the line, and seven paralleling stations). Land totaling 290,000 sq ft (6.7 acres) will be acquired from private property owners along the Peninsula Corridor in order to set up safety buffer zones between the overhead contact system and public property; PCJPB authorized eminent domain proceedings in July 2017 in case negotiations break down. Barriers will be installed where road and pedestrian bridges cross over tracks to prevent damage to the electrical wires. New electric trainsets will be purchased for use on the new electrified segment, while service from Tamien to Gilroy station, which is not planned to be electrified, will continue to be served with existing diesel locomotives.
The second part of the CalMod project is a positive train control system dubbed "CBOSS" (Communications Based Overlay Signal System), which is designed to meet federal safety requirements and as a condition set by the FRA to allow mixed traffic on the corridor. Key decisions in the development of CalMod can be traced back to the 1992 Feasibility Study, which recommended 25 kV AC overhead lines; the 1998 Rapid Rail Study, which recommended low-cost upgrades to first improve service and build demand; the 2006 Caltrain 2025 proposal, which proposed the use of lightweight electric multiple units; the 2009 FRA waiver, which imposed certain conditions on mixed traffic; and the 2012 memorandum of understanding with CHSRA, which resulted in a "blended" system to use the existing twin-track line as much as possible. The 2012 Blended Operations report concluded a new 8-mile (13 km) quad-track overtake section would allow Caltrain and CHSRA to coexist on the Peninsula Corridor with up to ten trains per peak hour: six Caltrain and four high-speed rail trains.
According to Caltrain, the electrification project will bring multiple benefits to the corridor. Firstly, electric trains can accelerate and decelerate more quickly than the existing diesel locomotives, resulting in faster and more frequent service. They will also replace Caltrain's current diesel locomotives and passenger cars, a significant portion of which are nearing the end of their lives. Additionally, electric trainsets are quieter and produce less air pollution that diesel locomotives, and the use of electric trains will lower Caltrain's fuel costs while increasing passenger revenue, due to an expected increase in ridership. Once complete, Caltrain expects to annually reduce carbon dioxide emissions by 176,000 metric tons and increase daily ridership by 21% by 2040. Daily service may be restored to Atherton and Broadway stations. Caltrain plans to complete the project by the end of 2021.
FRA waiver and CBOSS PTC
As a result of the blended plan, PCJPB mandated that Peninsula Corridor infrastructure and equipment should be compatible with future California High-Speed Rail Authority (CHSRA) trains. CHSRA had proposed that mandated speeds and transit times could be met by using lighter-weight vehicles that did not comply with Federal requirements. These required physical separation between FRA "compliant" and "non-compliant" rail vehicles and structural strength. Caltrain saw this as an opportunity to apply for an FRA waiver to run lighter-weight EMUs, which could accelerate faster and provide headways as low as five minutes. The December 2009 FRA waiver application detailed Caltrain's plans to prevent collisions: first, reduce the probability of collisions to nearly zero by employing temporal and spatial separation from freight rail and restricting freight traffic to the non-revenue hours, then mitigate the impact of a collision by deploying vehicles with crash energy management (CEM) structures, and then deployment of an enhanced positive train control system, which Caltrain named CBOSS, designed to check for speeding trains and protect rail workers.
Positive train control became a Federal mandate with the passing of the Rail Safety Improvement Act of 2008. After review, the FRA waiver was granted in May 2010, marking the first time lighter-weight EMUs were allowed to share rails with freight in the United States. The grant was conditioned on meeting nine additional requirements, including demonstrating minimum crashworthiness, seating, improving grade crossing, meeting FRA positive train control standards in Title 49 of the Code of Federal Regulations, part 236 with CBOSS, formalizing the temporal separation plan, and issuing a safety system program.
Rolling stock
The Stadler KISS double-decker EMU that Caltrain ordered will be compliant with the FRA alternative Tier-I crash-worthiness standard. Under the alternative standard, it will have Crash Energy Management (CEM) features that allow parts of the EMU to collapse whilst keeping the passenger seating area intact in the event of collision, instead of relying on pure structural strength as in the traditional Tier-I standard. The implementation of the alternative Tier-I standard results in a lighter train that will save energy and track maintenance cost. Coupled with the positive train control system that is being installed on the Caltrain line, Caltrain KISS trains will be allowed to operate in mixed traffic with heavier trains, such as Amtrak passenger trains and Union Pacific freight trains, instead of the temporal separation required in the 2009 waiver.
Because the existing Caltrain platforms are at a different height compared to proposed high-speed rail vehicles, the EMU trains will be equipped with doors at two heights, at 22-inch (560 mm) and 50.5-inch (1,280 mm) above-top-of-rail, allowing Caltrain to eventually transition from the existing 8-inch (200 mm) low platforms to CHSRA-compatible high platforms, enabling unassisted boarding of all passengers as specified by the Americans with Disabilities Act of 1990.
As Amtrak is in the process of replacing its fleet of EMD AEM-7 locomotives with Siemens ACS-64, PCJPB entered discussions to purchase several retired AEM-7s to test the electrification system and to serve as reserve locomotives in the event of EMU unavailability. Because of the delay in delivering ACS-64s, the target sale date for the AEM-7 was moved out to June 2016. The May 2017 PCEP Monthly Progress Report noted that PCJPB was drafting two requests for proposals: one to purchase an electric locomotive to test the electrification system, and another to refurbish an electric locomotive. By October 2017, the work in progress had identified two vendors: Mitsui for purchase, and Amtrak for refurbishment; in January 2018, contracts were ready to be awarded to those vendors. Mitsui owns several ex-Amtrak AEM-7 locomotives, and it has not been reported how many of these will be sold to Caltrain.
Funding
Funding for the $1.9 billion project comes from a mix of funds contributed by the California Department of Transportation, California High-Speed Rail Authority, California cap and trade revenue, Bay Area Air Quality Management District, Metropolitan Transportation Commission, the city and county of San Francisco, SamTrans, and Santa Clara Valley Transportation Authority. 32% of the funding, or $647 million, will come from Federal Transit Administration's Core Capacity grant, with the funding agreement approved on May 22, 2017 after a three-month delay. An additional $600 million comes from Proposition 1A funds that authorized the construction of high-speed rail, $113 million from cap and trade revenue, and the rest coming from local and regional sources.
Footnotes
References
External links
- Caltrain's Electrification Project Page
- "Caltrain Modernization Program". Peninsula Corridor Joint Powers Board. 2017. Retrieved March 25, 2017.
- "FRA-2009-0124 Caltrain - Waiver Petition". Federal Railroad Administration, Department of Transportation. 2016. Retrieved March 30, 2017.
Caltrain videos
- Caltrain's CBOSS and PTC Project Will Upgrade Safety on YouTube
- CalMod - Electrification and the Future of Caltrain on YouTube
Source of article : Wikipedia